Concrete Calculator
Last updated
Show steps
Enter the shape and size of your pour and this concrete calculator shows the volume in cubic feet, cubic yards and cubic metres, the number of 40, 60 or 80 lb bags you need (with a waste allowance) and an optional cost estimate.
How to calculate how much concrete you need
- Measure the length and width of the area and the thickness (depth) of the pour.
- Convert everything to one unit – for imperial, feet (4 inches = 4 ÷ 12 = 0.333 ft); for metric, metres (10 cm = 0.10 m).
- Multiply length × width × thickness to get cubic feet or cubic metres.
- Divide cubic feet by 27 to get cubic yards – the unit ready-mix suppliers use in the US.
- Add 5–10% for waste, spillage and an uneven base, then round up to the next bag or the supplier's minimum order step.
Worked example: a 10 × 10 ft patio slab, 4 inches thick. Volume = 10 × 10 × 0.333 = 33.33 ft³. In cubic yards, 33.33 ÷ 27 = 1.23 yd³ (0.94 m³). With 10% waste you need 36.67 ft³, or about 1.36 yd³.
How many bags of concrete do I need?
Bagged concrete is sold by weight, but what matters is how much volume each bag makes once mixed – its yield. Standard mixes yield roughly 0.60 ft³ per 80 lb bag, 0.45 ft³ per 60 lb bag and 0.30 ft³ per 40 lb bag. Divide your volume by the yield and round up. For the 10 × 10 ft slab with 10% waste: 36.67 ÷ 0.60 = 61.1, so buy 62 bags of 80 lb mix (or 82 bags of 60 lb, or 123 bags of 40 lb).

Yields vary between brands and product types (high-strength, fast-setting and fibre-reinforced mixes can differ), so the calculator lets you type the yield from your bag if it is different.
Formulas for every shape
| Shape | Formula | Example | Volume |
|---|---|---|---|
| Slab, patio, footing | L × W × T | 10 ft × 10 ft × 4 in | 33.33 ft³ |
| Wall | L × H × T | 20 ft × 8 ft × 8 in | 106.7 ft³ |
| Round column / post hole | π × r² × depth | 10 in hole × 3 ft | 1.64 ft³ |
| Post hole with post | π × r² × depth − post | 10 in hole, 3 ft, 4×4 post | 1.38 ft³ |
| Steps | W × Σ (rise × run × n) | 3 steps, 4 ft wide, 7 in rise, 11 in run | 12.83 ft³ |
Steps are the shape people most often under-order. Each step is a block that sits on top of the steps below it, so the bottom step is one rise tall, the second is two rises tall and so on. Add a landing as a separate slab. If the steps are built against a wall or slope with a sloped base, measure the real depth at several points and average them.
How thick should a concrete slab be?
| Project | Typical thickness | Notes |
|---|---|---|
| Garden path, shed base | 3–4 in (75–100 mm) | Light foot traffic |
| Patio | 4 in (100 mm) | Most common DIY slab |
| Residential driveway | 4–5 in (100–125 mm) | 5–6 in for heavier vehicles |
| Garage floor | 4–6 in (100–150 mm) | Check local building code |
| Hot tub pad | 4–6 in (100–150 mm) | Follow the manufacturer's spec |
| Footings | Per code and engineer | Depends on load and frost depth |
These are common starting points, not engineering advice. Structural work – foundations, retaining walls, suspended slabs – must follow your local building code and, where required, an engineer's design. Thickness has a big effect on the order: going from 4 to 5 inches adds 25% more concrete.
Ready-mix truck or bags?
For small jobs – post holes, a few steps, a shed base – bags mixed by hand or in a small mixer are usually easiest. As jobs grow past about one cubic yard (45 bags of 80 lb mix, more than 1.6 tonnes to lift), mixing becomes slow and it gets hard to place all the concrete before the first batch starts to set, which can leave cold joints. Ready-mix trucks deliver consistent concrete in one pour; most suppliers sell in quarter- or half-yard steps and may charge a short-load fee for small orders. Ask about minimum orders, waiting-time charges and whether a pump is needed if the truck cannot reach the pour.
How much does a yard of concrete weigh?
Normal-weight concrete weighs about 145–150 lb per cubic foot, so one cubic yard weighs roughly 4,000 lb (about 2 short tons). In metric, plan on about 2,400 kg per cubic metre. That weight matters for trailers, upper floors and wheelbarrows – a full wheelbarrow of wet concrete can easily exceed 200 lb.
Common mistakes that lead to short orders
- Entering thickness in feet instead of inches – a 4 ft 'slab' is twelve times too much.
- Measuring the planned thickness instead of the real depth of the excavation; dig depth often varies by an inch or more.
- Forgetting thickened edges, footings under a slab or the extra depth around post holes.
- Skipping the waste allowance. Running out mid-pour is far worse than having a few bags left.
- Ordering by bag weight without checking yield – a 60 lb bag does not make 60 lb worth of a 'yard'.
Before and after the pour
Compact the sub-base (usually gravel – see the gravel calculator) and set level forms before you order. After placing and finishing, keep the slab damp or covered so it does not dry too fast: concrete hardens by a chemical reaction with water, and it keeps gaining strength for weeks. Light foot traffic is often fine after a day or two, vehicles usually need much longer – follow the mix manufacturer's guidance. Control joints cut or tooled into the slab (a common rule is a spacing in feet of about 2–3 times the slab thickness in inches – roughly 8–12 ft for a 4 in slab) help cracks form in straight lines rather than randomly.
How much does concrete cost?
The calculator multiplies your volume by the price you enter, because prices vary a lot by region, season and supplier. To estimate a job: bagged mix = number of bags × price per bag; ready-mix = cubic yards (rounded up to the supplier's increment) × price per yard, plus any delivery, short-load, pump or Saturday charges. Add the cost of the gravel base, formwork lumber, reinforcement (rebar or mesh), and tools or labour. Get at least two written quotes for ready-mix, and ask exactly which fees apply to small loads.
Concrete mix strength and types
| Type | Typical use | What to know |
|---|---|---|
| General-purpose mix (about 3,000–4,000 psi / 20–28 MPa) | Patios, paths, steps, post footings | Most bagged mixes fall in this range – check the bag |
| High-strength mix (5,000 psi / 35 MPa and up) | Driveways, heavy loads, thinner sections | Costs more; follow the spec if one is given |
| Fast-setting mix | Fence and mailbox posts | Sets in minutes – mix small batches |
| Fibre-reinforced mix | Slabs where cracking is a concern | Fibres help control shrinkage cracks; not a substitute for structural steel |
| Mortar / sand mix | Bricklaying, toppings under 2 in | Not for structural slabs |
Strength is quoted as compressive strength after 28 days of curing, in psi (US) or MPa (metric). If a building plan or engineer specifies a strength, order that exact mix; for small DIY jobs a general-purpose mix is normally enough.
Ordering checklist
- Volume from the calculator, plus waste, rounded up.
- Mix type and strength (and air-entrained mix in freeze–thaw climates if your supplier recommends it).
- Slump (workability) if ordering ready-mix – ask the supplier what suits hand placing.
- Access: can the truck reach the forms, or do you need a pump, chute extension or wheelbarrows?
- Helpers and tools ready before the truck arrives – ready-mix sets on a timetable.
Sources
- Portland Cement Association – Concrete basics — cement.org
- QUIKRETE – Product yields printed on each bag — quikrete.com
Results are estimates for general information. Last reviewed: .

Written & built by
Zeeshan Nawaz
Calculator Developer · Tuff Search
Builds and tests Tuff Search calculators, turning published formulas and official sources into tools anyone can check.
FAQ
Frequently asked questions
Quick answers about the Concrete Calculator.
About 45. One cubic yard is 27 ft³ and an 80 lb bag yields about 0.60 ft³, so 27 ÷ 0.60 = 45 bags before waste.
At 4 inches thick, about 33.3 ft³ or 1.23 cubic yards – 56 bags of 80 lb mix, or about 62 with 10% waste.
A 10 in hole 3 ft deep with a 4×4 post needs about 1.4 ft³ – roughly 3 bags of 80 lb mix per hole with a little waste.
Divide by 27, because a cubic yard is 3 ft × 3 ft × 3 ft = 27 ft³.
Measure in metres and multiply length × width × thickness. A 4 m × 3 m slab, 0.10 m thick, needs 1.2 m³ before waste.
Add 5–10% for flat, well-formed slabs and up to 15% for uneven ground or irregular shapes.
No. Cement is one ingredient – the binder. Concrete is cement mixed with sand, gravel or crushed stone and water.
Still have a question? Email support@tuffsearch.com
Keep exploring
Related calculators
More calculators people use alongside this one.
Zeeshan Nawaz
Calculator Developer · Tuff Search
Builds and tests Tuff Search calculators. Each tool is based on published formulas and official sources, and is checked against worked test cases before it goes live.